A robot that has spent months inside the ruins of a nuclear reactor at the Fukushima Daiichi Nuclear Power Plant delivered a tiny sample of melted nuclear fuel on Thursday. Tokyo Electric Power Company Holdings (TEPCO), which manages the plant, considers this a significant step towards beginning the cleanup of hundreds of tons of melted fuel debris.

The sample, the size of a grain of rice, was placed into a secure container, marking the end of the robot’s mission. It is being transported to a glove box for size and weight measurements before being sent to outside laboratories for detailed analyses over the coming months.

Plant chief Akira Ono stated that the sample will provide vital data to plan a decommissioning strategy, develop necessary technology and robots, and understand how the accident unfolded.

TEPCO spokesperson Kenichi Takahara told reporters on Thursday that the first sample alone is insufficient and additional small-scale sampling missions will be necessary to gather more data. “It may take time, but we will steadily tackle decommissioning,” Takahara said.

Despite multiple probes in the years since the 2011 disaster that devastated the plant and forced thousands of nearby residents to leave their homes, much about the site’s highly radioactive interior remains a mystery.

The sample, the first to be retrieved from inside a reactor, was significantly less radioactive than expected. Officials had been concerned that it might be too radioactive to be safely tested even with heavy protective gear, and set an upper limit for removal out of the reactor. The sample came in well under the limit.

This has led some to question whether the robot extracted the fuel it was looking for from an area in which previous probes have detected much higher levels of radioactive contamination. However, TEPCO officials insist they believe the sample is melted fuel.

The extendable robot, nicknamed Telesco, first began its mission in August with a plan for a two-week round trip, after previous missions had been delayed since 2021. But progress was suspended twice due to mishaps — the first involving an assembly error that took nearly three weeks to fix, and the second a camera failure.

On Oct. 30, it clipped a sample weighting less than 3 grams (.01 ounces) from the surface of a mound of melted fuel debris sitting on the bottom of the primary containment vessel of the Unit 2 reactor, TEPCO said.

Three days later, the robot returned to an enclosed container, as workers in full hazmat gear slowly pulled it out.

On Thursday, the gravel, whose radioactivity earlier this week recorded far below the upper limit set for its environmental and health safety, was placed into a safe container for removal out of the compartment.

The sample return marks the first time the melted fuel is retrieved out of the containment vessel.

Fukushima Daiichi lost its key cooling systems during a 2011 earthquake and tsunami, causing meltdowns in its three reactors. An estimated 880 tons of fatally radioactive melted fuel remains in them.

The government and TEPCO have set a 30-to-40-year target to finish the cleanup by 2051, which experts say is overly optimistic and should be updated. Some say it would take for a century or longer.

TEPCO said there have been some delays but “there will be no impact on the entire decommissioning process.”

No specific plans for the full removal of the fuel debris or its final disposal have been decided.